Heliostar Announces PEA for Ana Paula Underground with Strong Economics and Sustainable Cash Generation

Heliostar Announces PEA for Ana Paula Underground with Strong Economics and Sustainable Cash Generation

Heliostar Metals Ltd. (TSXV: HSTR) (OTCQX: HSTXF) (FSE: RGG1)

Date: November 6, 2025 – 6:30 AM EST

Highlights:
  • Base Case: US$426M post-tax NPV₅, 28.1% IRR, 2.9-year payback at US$2,400/oz Au
  • Upside Case: US$1.01B post-tax NPV₅, 51.3% IRR, 1.9-year payback at US$3,800/oz Au
  • 874,700 oz Au over 9-year mine life averaging 101 koz/yr after ramp-up
  • Life-of-mine AISC: US$1,011/oz (lowest 13% globally) with US$300M CAPEX
  • Average annual after-tax FCF: US$93.8M @ US$2,400/oz Au (US$168M @ US$3,800/oz)
  • Plan to bring Ana Paula into production in 2028 following Feasibility Study

VANCOUVER, BC — Heliostar Metals Ltd. (“Heliostar” or the “Company”) is pleased to announce the results of a Preliminary Economic Assessment (“PEA”) evaluating the potential for underground mine development at the Ana Paula Project in Guerrero, Mexico.

Heliostar CEO Charles Funk commented: “Today’s PEA demonstrates Ana Paula can be a low-CAPEX, high-margin gold mine… we are excited at the prospect of bringing Ana Paula into production as a robust free-cash-flow-generating mine that will underpin Heliostar’s share price for the next decade.”

Figure 1 - Ana Paula Resource Distribution
Figure 1: Ana Paula Resource with Gold Ounce and Grade Distribution of Mill Feed by Level.
Figure 2 - Underground Development Schedule
Figure 2: Ana Paula Underground Development Schedule and Stope Layout Over Life of Mine.
Figure 3 - Planned Production Schedule
Figure 3: Planned Ana Paula Production Schedule.
Figure 4 - Process Flow Sheet
Figure 4: Ana Paula Process Flow Sheet.

Ana Paula PEA Mineral Resource Estimate

ClassificationKilotonnes (kt)Gold Grade (g/t)Contained Gold Ounces
Measured1,3007.60317,000
Indicated2,9704.44424,000
Measured & Indicated4,2705.40742,000
Inferred4,0403.96514,000

Reported insitu using 2014 CIM standards; effective date July 30, 2025; cutoff 2.10 g/t Au. Not Mineral Reserves; economic viability not demonstrated.

Ana Paula PEA Mill Feed Inventory

ClassificationKilotonnes (kt)Gold Grade (g/t)Contained Gold OuncesContained Gold Ounces (%)
Measured1,1038.12288,00030%
Indicated2,3054.81356,00037%
Measured & Indicated3,4085.88644,00066%
Inferred2,0245.04327,00034%
Dilution1930%
Total5,6255.37972,000100%

Forecast Production Highlights

ParameterValueUnits
Mill Feed (LOM)5,625kt
Gold Grade (LOM)5.37g/t Au
Gold Produced (LOM)875koz
Process Recovery90%
Life of Mine9years
Average Annual Production101koz/yr

Forecast Financial Highlights

MetricValueUnits
Average Cash Cost923US$/oz
AISC1,011US$/oz
Initial Capital Cost300.1M
Total Sustaining Capital73.2M
Total LOM Capital376.3M

Forecast Return Estimates (by Gold Price)

Gold Price (US$/oz)IRRNPV₅ (US$M)Payback (yrs)
2,40028.1%4262.9
3,80051.3%1,0121.9

Total Operating Cost Summary

Operating CostsUS$/oz AuUS$/t feed
Total Mining42164.85
Total Processing22734.94
BIOX Processing8712.59
G&A507.75
Refinery & Transport111.63
Cash Operating Costs709109.17
Production Taxes16625.53
Royalties487.36
Total Cash Costs922142.06
Sustaining Capital8413.01
Total AISC1,011155.07

Forecast Capital Cost Summary

Capital CostsInitial (US$M)Sustaining (US$M)Total LOM (US$M)
Underground Mining43.470.1113.5
Process Plant61.661.6
BIOX Plant45.845.8
Tailings Management26.93.130.0
Infrastructure20.220.2
Power/Substation6.26.2
Camp Expansion6.86.8
Total Direct Costs210.973.2284.1
Indirects + EPCM + Contingency89.23.092.2
Total300.176.2376.3

Summary Economic Results

MetricUnitsAfter TaxBefore Tax
Total CashflowUS$ M631.3903.1
Average Annual CashflowUS$ M70.1100.3
NPV₅ (Base Case)US$ M426.0642.7
IRR%28.138.0
PaybackYears2.92.4

Gold Price Sensitivity Analysis

Gold Price (US$/oz)Net Cash Flow (US$M)NPV₅ (US$M)IRR (%)Payback (yrs)
1,6001978810.64.9
2,00041725920.03.5
2,40063142628.12.9
3,00095467738.72.4
3,8001,3831,01251.31.9
4,0001,4901,09654.21.8

Next Steps

Heliostar has completed 10,909 m of its 15,000 m drill program with assays expected every 4–6 weeks. Objectives include converting Inferred ounces to higher confidence categories, supporting the Feasibility Study, and exploring targets north of the High Grade Panel. A permit amendment will be submitted in Q1 2026 to transition from open-pit to underground operations.

The Company plans to extend its existing 400 m decline by 1.2 km as part of an early works program (~US$15M), funded through free cash flow from its La Colorada and San Agustin mines. This will provide early access, facilitate a bulk sample, and establish underground drill platforms to test extensions down plunge.

About Heliostar Metals Ltd.

Heliostar is a gold mining company operating the La Colorada Mine (Sonora) and San Agustin Mine (Durango), Mexico, with development-stage assets including Ana Paula (Guerrero), Cerro del Gallo (Guanajuato), San Antonio (Baja Sur), and the Unga Project (Alaska, USA).

Contact:
Charles Funk, CEO — charles.funk@heliostarmetals.com — +1 844-753-0045
Rob Grey, IR Manager — rob.grey@heliostarmetals.com — +1 844-753-0045

Disclaimer: Past performance is not an indicator of future returns. NIA is not an investment advisor and does not provide investment advice. Always do your own research. NIA has received compensation from HSTR of US$30,000 cash for three months of coverage and could receive up to US$100,000 cash for twelve months. This content is for informational and educational purposes only and does not provide investment advice.